Searching over 5,500,000 cases.


searching
Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.

Moorefield Construction, Inc. v. Concrete Construction, Inc.

Court of Appeals of Arkansas, Division II

December 11, 2019

MOOREFIELD CONSTRUCTION, INC., Appellant
v.
R.L. HURST CONCRETE CONSTRUCTION, INC. a/k/a R.L. Hurst, Appellee

Page 211

          APPEAL FROM THE GARLAND COUNTY CIRCUIT COURT [NO. 26CV-14-884], HONORABLE MARCIA R. HEARNSBERGER, JUDGE

         Gill Ragon Owen, P.A., Little Rock, by: Roger H. Fitzgibbon, Jr., for appellant.

         Steve Westerfield, Hot Springs National Park, for appellee.

         OPINION

         N. MARK KLAPPENBACH, Judge

Page 212

          Appellant Moorefield Construction, Inc., appeals the judgment entered against it and in favor of appellee R.L. Hurst Concrete Construction, Inc., a/k/a R.L. Hurst for $14,596.67. Hurst had filed a breach-of-contract complaint against Moorefield contending that Moorefield failed to pay the full contract price on the concrete parking-lot repair job that Hurst completed. The circuit court found, after a bench trial, that Hurst completed the contracted work, that a subsequently signed amendment to the contract that reduced the contract price was not supported by consideration, and that Hurst was granted judgment for the outstanding $14,596.67 plus court costs and a reasonable attorney’s fee. Moorefield contends that the circuit court’s findings in the November 19, 2018 judgment are clearly erroneous.[1] We disagree and affirm.

         In order to prove a breach-of-contract claim, one must prove "the existence of an agreement, breach of the agreement, and resulting damages." Barnes v. Wagoner, 2019 Ark.App. 174, 573 S.W.3d 594. There is no dispute that in May 2013, Moorefield and Hurst entered into a written contract for Hurst to repair paved areas on the exterior of a Wal-Mart store, specifically to address cracking in the concrete, for which Moorefield would pay $58,000. The "scope of work" was described as Hurst’s completing "all barricade, removal of concrete, doweling of concrete and placement of concrete" in "strict accordance with the contract documents" and the photographs attached as exhibits to the contract. The contract required Hurst to complete "all work indicated or implied on the drawings." Hurst promptly started the job and finished it in mid-June. Moorefield had made substantial payments on the $58,000 contract price, and Moorefield was satisfied with Hurst’s work, but thousands of dollars remained unpaid. Hurst sent Moorefield an invoice for the outstanding balance.

          On or about July 1, 2013, Moorefield determined that not all the originally identified concrete needed to be removed and repaired, so it wanted to pay a proportionately lower contract price. Moorefield offered Hurst a $10,000 check as payment in full, which was $14,596.67 less than the original outstanding balance due. Hurst believed that all the work encompassed by the contract had been done. Moorefield, however, presented Hurst an "Amendment to Subcontract" that stated that the 9000 square feet of concrete work in the original contract was actually 6735 square feet, so based on a per-square-foot price, the contract price was now $43,403.33. This reduced the $58,000 original contract by $14,596.67. According to Mr. Hurst, he signed the amendment under duress that day because Hurst needed the $10,000 payment immediately to continue operating the business. Moorefield made no further payments.

          In December 2014, Hurst filed the breach-of-contract action contending that it had satisfactorily completed the job pursuant to the original contract, that it was owed the full contract price, that the subsequent contract amendment was not supported by consideration but was instead entered into under duress, and that

Page 213

Moorefield breached the original contract by not paying what was owed. Moorefield answered the complaint with a general denial of all allegations. In its pretrial brief, Moorefield contended that "it was determined during the progress of this work that not all of the originally identified concrete would need to be removed and replaced" leading to the preparation of a "Change Order" to reduce the contract price based on the reduced scope of work Hurst was required to perform. Moorefield asserted that Hurst consented to and signed the "Change Order."

          At the bench trial, Mr. Hurst testified that his initial bid on this concrete-repair job was about $80,000, which he lowered to $70,000, but the final agreed flat price was $58,000. Mr. Hurst explained that in making a bid on the job, there are "just many, many factors" to consider, such as the transportation necessitated by the sixty miles this job was from his place of business, the area of work to be done, and the equipment and people required to do the work. Hurst said that he completed the work exactly as the contract required, that Wal-Mart and Moorefield accepted the work, and that there was no "by-the-square-foot-of-concrete" contract. Mr. Hurst said Moorefield owed approximately $24,000 after the job was completed, and he sent Moorefield an invoice in mid-June.

          On July 1, 2013, according to Mr. Hurst, Moorefield (through its project manager, Josh Daves) offered Hurst a $10,000 check but only if Hurst agreed that this would be payment in full. According to Mr. Hurst, Daves required him to change his invoice, sign a lien waiver, and amend the contract in order to get the check. Mr. Hurst testified that he signed the amendment that day under duress, "absolutely had to have" the payment to keep his business going, and felt he had no choice. Mr. Hurst stated that Daves came up with the square-foot calculation, which was nowhere in the original contract. Mr. ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.